Knowledge Hub

Factora Academy

Knowledge Hub · Courses · FactoraERP · System Integrators · 12 min

Cut-over runbook

Expert · Go-Live and Hypercare · Step 1: Go-live readiness

Introduction

What this covers

How to write a minute-by-minute cut-over with owners, and how to rehearse it once before the real event.

Why it matters on the floor

An unrehearsed runbook skips the reconcile or the freeze. The rehearsal is where that skip is cheap.

By the end you can

  • Write each step with a clock time and one owner
  • Include freeze, delta load, reconcile, user notice, and read-only on the old system
  • Rehearse the runbook once and correct it before the real cut-over

About 12 minutes. Prerequisites: Readiness criteria.

Expert · Go-Live and Hypercare Module: Step 1: Go-live readiness

Runbook

A minute-by-minute plan with owners. Rehearse it once before the real event.

Learning objectives

  • Write each step with a clock time and one owner
  • Include freeze, delta load, reconcile, user notice, and read-only on the old system
  • Rehearse the runbook once and correct it before the real cut-over

Walk the screen

  1. One row per step: time, action, owner, evidence it is done.
  2. The first rows are the freeze announcement and the check that the old system will not take new edits.
  3. The middle rows are the delta load and the reconcile of quantities.
  4. The later rows tell each job their login works and where to log the next truck.
  5. The last rows set the old system read-only and name the hypercare contact.
  6. Rehearse with the same owners. Time it. Change any step that depended on someone who was not in the room.

Worked example

The rehearsal discovers that the warehouse lead has no login. That step is added the week before, not discovered at 18:00 on cut-over day. The real event follows the corrected times. The reconcile evidence is a written total, not a nod.

Common mistakes

  • A runbook that says 'migrate data' as a single line.
  • Rehearsing only in conversation.
  • Changing owners on the day without updating the page.

Recap

  • The runbook is minute by minute, with owners.
  • Rehearse it once before the real event.
  • Evidence is a total or a signature, not a feeling.

Quiz for this module: Step 1: Go-live readiness.

Create a free account or log in to save this lesson on your progress.

Check understanding

Progress is stored in this browser until you log in. Passing is 70%.

1. When should go/no-go criteria be agreed?
2. A cut-over runbook should be rehearsed.
3. An open reconcile on cut-over morning means
4. A runbook step should have one owner and evidence it is done.