Phasing the rollout

Foundation · Implementation Methodology · Step 1: Scoping the project

Introduction

What this covers

How to go live first with intake through warehouse, then add production, sales, and finance, so each phase is small enough to trust.

Why it matters on the floor

A big-bang go-live hides which step broke. A short phase builds confidence and keeps a rollback obvious.

By the end you can

  • Put intake to warehouse in the first phase
  • Add production, then sales, then finance only after the previous phase is in daily use
  • Keep each phase inside the signed scope

About 12 minutes. Prerequisites: Discovery workshops.

Foundation · Implementation Methodology Module: Step 1: Scoping the project

Phases

Go live with the core flow first (intake to warehouse), then add production, sales and finance. Smaller phases reduce risk and build confidence.

Learning objectives

  • Put intake to warehouse in the first phase
  • Add production, then sales, then finance only after the previous phase is in daily use
  • Keep each phase inside the signed scope

Walk the screen

  1. Read the signed scope. Draw phases under it. Do not add a module the scope excluded.
  2. Phase one is the core flow: Material Intake, lab, approval, and Warehouse. People must be able to find a lot.
  3. Next phase adds Production, sorting, and work orders if the scope includes them.
  4. Sales and dispatch follow once finished goods exist in the warehouse.
  5. Finance and payroll come after the operational quantities are trusted. Do not open Payroll on day one to 'get it over with'.
  6. Each phase has its own go-live date. The next phase does not start because the calendar said so if the previous one is still on paper.

Worked example

The sample mill goes live on Monday with intake and warehouse only. Production is the following month. A request to add CRM in week one is written onto a later phase because it was not in the signed scope and it is not the core flow.

Common mistakes

  • Turning every module on during the same weekend.
  • Starting with payroll because finance is the loudest voice.
  • Letting phase two begin while trucks are still logged on paper.

Recap

  • Smaller phases reduce risk.
  • Core flow first: intake to warehouse. Then production, sales, and finance.
  • Stay inside the signed scope.

Quiz for this module: Step 1: Scoping the project.

Create a free account or log in to save this lesson on your progress.

Check understanding

Progress is stored in this browser until you log in. Passing is 70%.

1. What should discovery workshops end with?
2. Phasing a rollout reduces risk.
3. The first phase of a rollout should be
4. A module excluded from the signed scope can be added quietly in week three.