Readiness criteria

Prerequisite: Data Migration and Advanced Configuration. · Expert · Go-Live and Hypercare · Step 1: Go-live readiness

Introduction

What this covers

How to agree go and no-go criteria before the weekend: user acceptance signed, data reconciled, users trained, a support rota, and a rollback plan.

Why it matters on the floor

Criteria invented on the morning of go-live are just the wish to start. Agreed criteria can stop a start that is not ready.

By the end you can

  • Write the criteria before cut-over day
  • Require signed user acceptance, reconciled data, trained users, a support rota, and a written rollback
  • Call no-go when a criterion is open, even if the date is unpopular

About 12 minutes. Prerequisites: None. This opens go-live.

Expert · Go-Live and Hypercare Module: Step 1: Go-live readiness

Run a controlled go-live, support users through the first weeks and hand over to the customer.

Prerequisite: Data Migration and Advanced Configuration.

Decide go or no-go with evidence.

Go / no-go

Agree criteria in advance: UAT signed, data reconciled, users trained, support rota in place, rollback plan documented.

Learning objectives

  • Write the criteria before cut-over day
  • Require signed user acceptance, reconciled data, trained users, a support rota, and a written rollback
  • Call no-go when a criterion is open, even if the date is unpopular

Walk the screen

  1. Draft the list in the project room, not in the cut-over hour: UAT signed, data reconciled, users trained, support rota in place, rollback plan documented.
  2. UAT signed means the users signed the scenarios, not that the consultant finished clicking.
  3. Data reconciled means the cut-over totals, not last month's trial.
  4. Trained users means each job in this phase has a named person who has logged in as themselves.
  5. The rota names who answers on day one and day two, including a deputy.
  6. Rollback says how you return to the read-only legacy path if the reconcile fails. Read it aloud before the go decision.

Worked example

Saturday morning the reconcile is short by one supplier. The criteria say data reconciled. The lead calls no-go, the old system stays the place for today's trucks, and the missing supplier is fixed before a second attempt. The date moving is the plan working.

Common mistakes

  • Adding 'we feel ready' as a criterion on the day.
  • Starting with an unsigned test because the sponsor is travelling.
  • A rota that is only one person.

Recap

  • Agree go and no-go criteria in advance.
  • The list is signed tests, reconciled data, trained users, a rota, and a rollback.
  • An open criterion is a no-go.