User acceptance testing

Foundation · Implementation Methodology · Step 2: Configure, train, accept · badge Implementation Ready

Introduction

What this covers

How the factory users run their own scenarios, log defects, retest fixes, and sign off before go-live.

Why it matters on the floor

A consultant clicking through happy paths will miss the mixed load and the wrong price. The user's scenario is the test.

By the end you can

  • Have the users run scenarios from their own work, including a correction and a failure
  • Log defects, fix them, and retest the same scenario
  • Get sign-off before go-live, and treat an open blocker as a no-go

About 12 minutes. Prerequisites: Configuration checklist.

Foundation · Implementation Methodology Module: Step 2: Configure, train, accept

UAT

Users run real scenarios from their own work. Log defects, fix, retest, and get sign-off before go-live.

Learning objectives

  • Have the users run scenarios from their own work, including a correction and a failure
  • Log defects, fix them, and retest the same scenario
  • Get sign-off before go-live, and treat an open blocker as a no-go

Walk the screen

  1. Write scenarios from the workshop, not from a generic script. Include a single-material truck, a mixed load logged as separate intakes, a lab fail, and a price correction.
  2. The receiving user logs the intake. The lab user enters results. The approver uses Request Correction when the price is wrong and Reject when the material fails.
  3. Each defect is logged with the screen, the lot, and what happened. 'Does not work' is not a defect.
  4. Fix, then the same user retests. The consultant does not retest alone and call it accepted.
  5. Sign-off is a named user per scenario. No sign-off, no go-live.
  6. Scenarios outside the phase are not failed tests. They are noted as later phase.

Worked example

The lab user fails a demo lot and checks that it cannot be consumed on a production run. The approver sends a wrong price back with Request Correction. Both scenarios are signed. A wish for a new CRM column is logged as out of phase, not as a defect.

Common mistakes

  • The consultant running every script while users watch.
  • Closing a defect without the user retrying it.
  • Signing off with a blocker still open because the date is near.

Recap

  • Users run real scenarios. Consultants do not accept the system for them.
  • Defects are fixed and retested before sign-off.
  • Sign-off happens before go-live.

Badge

Completing this level is the badge Implementation Ready.

Badge on completion: Implementation Ready

Quiz for this module: Step 2: Configure, train, accept.

Create a free account or log in to save this lesson on your progress.

Check understanding

Progress is stored in this browser until you log in. Passing is 70%.

1. Who should run acceptance testing?
2. Sign-off should happen before go-live.
3. A supplier used in an intake test must
4. The consultant retesting alone is enough to accept a fix.