Raising an NCR and running CAPA

Professional · Quality and Compliance in Practice · Step 1: Inspections and non-conformances

Introduction

What this covers

How to raise an NCR with a clear title and severity, move it through investigation and CAPA, and close it only after the preventive action is verified.

Why it matters on the floor

Closing an NCR when the lot is quarantined fixes today and leaves the next lot exposed. Preventive action is the point of the record.

By the end you can

  • Raise an NCR with a title, severity, and what happened, where, and when
  • Separate the corrective action from the preventive action
  • Close only after the preventive action is verified, using the five-whys root cause

About 12 minutes. Prerequisites: Incoming quality control.

Professional · Quality and Compliance in Practice Module: Step 1: Inspections and non-conformances

Non-conformance reports

When something does not meet a standard - a failed test, a process not followed, a customer complaint - raise an NCR in Audits & NCR.

A good NCR has:

  1. A clear title - "Foreign material found in Lot 4471"
  2. Severity - how serious the risk is to safety, quality or compliance
  3. What happened, where and when, with evidence

The NCR lifecycle

Open -> Under Investigation -> CAPA In Progress -> Pending Verification -> Closed

CAPA means Corrective and Preventive Action:

  • Corrective - fix this problem (quarantine the lot, re-sort it)
  • Preventive - stop it happening again (add a sieve, retrain staff, change a supplier)

Root cause - ask "why" five times

The lot had stones. Why? The supplier did not sieve. Why? Their sieve broke. Why? No spare. Why? No maintenance plan. Root cause: supplier has no equipment maintenance plan.

Only close an NCR after verifying the preventive action actually worked.

Learning objectives

  • Raise an NCR with a title, severity, and what happened, where, and when
  • Separate the corrective action from the preventive action
  • Close only after the preventive action is verified, using the five-whys root cause

Walk the screen

Open NCR-0001 for foreign material in Lot 4471
NCR-0001 is major and still open. Close it only after the preventive action is verified.
  1. Open Audits and NCR at /f/<company-slug>/audits-ncr. NCR-0001 is already open: Foreign material in Lot 4471, severity major.
  2. Title it with the fact, for example foreign material found in Lot 4471. Set severity for safety, quality, or compliance.
  3. Move the status deliberately: Open, Under Investigation, CAPA In Progress, Pending Verification, Closed.
  4. Corrective action fixes this lot, such as quarantine or re-sort. Preventive action stops the next one, such as a sieve, retraining, or a supplier change.
  5. Ask why until the cause is a system gap. Stones in the lot can end at a supplier with no maintenance plan.
  6. Verify the preventive action worked, then close. Do not close at year end because the list looks old.

Worked example

NCR-0001 is open and major, titled Foreign material in Lot 4471. Corrective action quarantines the lot. Five whys reach a supplier sieve with no spare and no maintenance plan. You do not close NCR-0001 when the lot is quarantined. You close it after the supplier's maintenance plan is checked.

Practical tip: keep the NCR number in the handover. NCR-0001 is easier to find than 'the stones one'.

Recap

  • CAPA is corrective and preventive action.
  • The path ends at Closed only after verification.
  • Root cause is the last why, not the first symptom.

Quiz for this module: Step 1: Inspections and non-conformances.

Create a free account or log in to save this lesson on your progress.

Check understanding

Progress is stored in this browser until you log in. Passing is 70%.

1. What does CAPA stand for?
2. Which check happens before dispatch?
3. When should an NCR be closed?
4. Conditionally Accepted material can be used with agreed limits.